We will be finalizing the migration maintenance on Cluster1 Win31 starting at 10:30PM Tonight, there will be a few moments of outage as the IP addresses move between servers, and we test on the new server to ensure all sites are operational.
The final sync is still going at the moment. Probably another 20 minutes.
Ok sync still going more file changes in a few hours than I expected…
The sync is done, working on the file permissions post sync then the final step of moving IP addresses.
Still a little ways away from doing the IP swap, as the permissions process is ongoing now.
IPs being switched across now!
Done, tested 5 domains and working well, will be checking a few more now.